Holtec Announces Start of Fuel Loading at Palisades Nuclear Power Plant, Advancing Toward Restart

August 31, 2026

Power Off, Jackery On: Jackery Marks National Preparedness Month with Home Backup Built for the Fall Storm Season

August 31, 2026

Bangalore and Mumbai Water Purifier Rentals Turn on Specification Fit and Service Speed in 2026 as Low TDS Readings Mask Bacteriological Risk – ₹292/Month Non-RO and ₹391/Month In-House Units From Rentomojo

August 31, 2026

Judge grants injunction suspending new Ontario bail payment requirements

August 31, 2026
Facebook X (Twitter) Instagram
Finance Pro
Facebook X (Twitter) Instagram
Daily Guardian
Subscribe
  • Home
  • News
  • Politics
  • Business
  • Entertainment
  • Lifestyle
  • Health
  • Sports
  • Technology
  • Climate
  • Auto
  • Travel
  • Web Stories
Daily Guardian
Home » Holtec Announces Start of Fuel Loading at Palisades Nuclear Power Plant, Advancing Toward Restart
Press Release

Holtec Announces Start of Fuel Loading at Palisades Nuclear Power Plant, Advancing Toward Restart

By News RoomAugust 31, 20265 Mins Read
Holtec Announces Start of Fuel Loading at Palisades Nuclear Power Plant, Advancing Toward Restart
Share
Facebook Twitter LinkedIn Pinterest Email

Fuel loading marks key milestone toward the first-ever restart of a permanently shuttered U.S. commercial nuclear power plant

Palisades Reactor Cavity and New Fuel Handling Machine

Palisades Reactor Cavity and New Fuel Handling Machine

COVERT TOWNSHIP, Mich., Aug. 31, 2026 (GLOBE NEWSWIRE) — Holtec Nuclear Corporation (“Holtec” or the “Company”) announced today that its Palisades Nuclear Power Plant has begun loading nuclear fuel into the plant’s reactor vessel, marking a historic milestone as Palisades advances toward becoming the first commercial U.S. nuclear power plant to return to service after entering decommissioning. The start of fuel loading places Palisades in Mode 6 under the plant’s Technical Specifications, a required step on the path to commercial operation.

The reactor core consists of 204 fuel assemblies, including new fuel and partially used fuel from the plant’s most recent operating cycles, and is designed to support Palisades’ 805-megawatt electric output. The fuel-loading milestone follows more than two years of extensive inspection, maintenance, refurbishment, testing, and equipment upgrades across the station intended to ensure reliability and resiliency for long-term operation.

Major restart work completed at the plant included reinforcement of tubes in the two steam generators; removal of accumulated corrosive species from the steam generation space; replacement of the plant’s control rod drive mechanism nozzles; chemical decontamination and passivation of the primary system; reactor vessel inspections; and numerous equipment upgrades and modernization projects. In several areas, the scope of planned work was expanded to further enhance the plant’s long-term reliability.

Fuel loading is being conducted in accordance with plant procedures and Technical Specifications. Following completion of fuel loading, Palisades will progress through a series of required testing, inspections, and startup activities as plant systems are declared fit for operation. These activities are being led by Holtec Nuclear Corporation Chief Nuclear Officer Fadi Diya, Site Vice President Mike Schultheis, and Plant General Manager Adam Eastridge, together with the site’s leadership team, with independent oversight from the Palisades Nuclear Safety Review Board, chaired by industry veteran Michael Rencheck.

“Loading fuel into the Palisades reactor is an important milestone and a reflection of the tremendous effort of the men and women who have brought this plant to this point,” said Fadi Diya, Chief Nuclear Officer of Holtec Nuclear Corporation. “I am proud to lead an organization with such talented and dedicated people who have a deep sense of pride in this plant and a deep commitment to their community. We remain focused on disciplined execution of the remaining work and returning Palisades to safe and reliable operation.”

Holtec recognized the significant contributions of the many organizations supporting the restart effort, including the Institute of Nuclear Power Operations, peer nuclear facilities, the Nuclear Energy Institute, and the numerous contractors and industry partners that have provided specialized expertise throughout the project.

The restart of Palisades has been made possible by financial support from the State of Michigan, a loan from the U.S. Department of Energy, and long-term power purchase agreements with Wolverine Power Cooperative and Hoosier Energy. Holtec expressed its gratitude to its federal, state, and community partners for their confidence in the Company’s ability to return Palisades to service. The plant is now proceeding through its remaining pre-startup activities ahead of resuming commercial operation.

Cautionary Statement Regarding Forward-Looking Statements
This release contains forward-looking statements, including statements regarding the Company’s planned restart of the Palisades Nuclear Power Plant. Forward-looking statements involve risks, contingencies, and uncertainties, which are difficult to predict and many of which are beyond our control. The forward-looking statements in this post speak only as of the date of this post. We undertake no obligation to update these statements unless required by law, and we caution you not to place undue reliance on them. 

About Holtec Nuclear Corporation
Holtec is a U.S.-headquartered, multinational technology company focused on clean energy, with its principal business centered on nuclear power generation and an expanding presence in adjacent clean energy generation solutions and long-duration energy storage. The Company is the owner/developer of the SMR-300 advanced small modular reactor featuring passive safety systems, and currently expects the first two units to be deployed at the Company-owned Palisades site in Michigan. Holtec is also refurbishing the Palisades nuclear power plant, which would be the first commercial nuclear reactor in the United States to be repowered after permanent shutdown. Holtec is the NRC-authorized Operator for the Palisades plant.

The Company’s business profile is distinguished by the ownership of nearly 220 granted patents, a substantial portfolio of proprietary technologies and trade secrets, three large U.S.-based manufacturing facilities for nuclear fabrication and operations on five continents. The Company has provided products and services to a client base of more than 150 nuclear reactors worldwide. Holtec’s technical capabilities include reactor design, reactor operations, engineering, licensing, manufacturing, construction, commissioning, and decommissioning services. As such, Holtec believes that it is well-positioned to help catalyze the growth of the nuclear power industry in the U.S. and around the world. The Company is also expanding its activities in solar energy and long-duration energy storage technologies intended to enhance renewable energy reliability and complement its SMR-300 product line.

Contact:
Patrick O’Brien, Director of Government Affairs and Communications
Phone: (508) 494-4254 | Email: [email protected]

ICR
[email protected]

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/9f32736c-a2f7-482f-982b-f0add305acc6

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

Keep Reading

OneLayer Turns Real Cellular Threats Into Automatic Detections

Power Off, Jackery On: Jackery Marks National Preparedness Month with Home Backup Built for the Fall Storm Season

Bangalore and Mumbai Water Purifier Rentals Turn on Specification Fit and Service Speed in 2026 as Low TDS Readings Mask Bacteriological Risk – ₹292/Month Non-RO and ₹391/Month In-House Units From Rentomojo

Articuler Launches AI-Native Professional Matching Platform to Connect Solo Operators With the People They Need

Hagens Berman Alerts Capricor Therapeutics, Inc. (NASDAQ: CAPR) Investors to FDA Review Extension for Deramiocel Amid Ongoing Securities Class Action and September 28 Lead Plaintiff Deadline

Joni and Friends Celebrates the Distribution of its 250,000th Wheelchair

Wix.com (WIX) Faces Securities Class Action Amid Scrutiny Over Vibe Coding Transition, Competitive and Financial Positioning – Hagens Berman

Crypto News: Pepeto Announces Its Presale Passed $10.9M Fast And 2026 SpaceX Proves Why Crypto Presales Beat Stocks

Zoomex Concludes High-Impact "Trade the Tide" Event at Coinfest Asia 2026, Accelerating SEA Market Expansion

Editors Picks

Holtec Announces Start of Fuel Loading at Palisades Nuclear Power Plant, Advancing Toward Restart

August 31, 2026

Power Off, Jackery On: Jackery Marks National Preparedness Month with Home Backup Built for the Fall Storm Season

August 31, 2026

Bangalore and Mumbai Water Purifier Rentals Turn on Specification Fit and Service Speed in 2026 as Low TDS Readings Mask Bacteriological Risk – ₹292/Month Non-RO and ₹391/Month In-House Units From Rentomojo

August 31, 2026

Judge grants injunction suspending new Ontario bail payment requirements

August 31, 2026

Latest News

Articuler Launches AI-Native Professional Matching Platform to Connect Solo Operators With the People They Need

August 31, 2026

Phil Schiller is leaving his biggest jobs at Apple

August 31, 2026

Hagens Berman Alerts Capricor Therapeutics, Inc. (NASDAQ: CAPR) Investors to FDA Review Extension for Deramiocel Amid Ongoing Securities Class Action and September 28 Lead Plaintiff Deadline

August 31, 2026
Facebook X (Twitter) Pinterest TikTok Instagram
© 2026 Daily Guardian Canada. All Rights Reserved.
  • Privacy Policy
  • Terms
  • Advertise
  • Contact

Type above and press Enter to search. Press Esc to cancel.

Go to mobile version